Procurement.

Municipal sponsors may use their own procurement standards currently in place for trail grant related procurement activities and contract work. For not-for-profit sponsors, the procurement procedures are based on the total contract amount or on the total cost of materials, equipment, or services to be purchased or contracted as follows:

Multiple purchasing is not permitted. For example, purchasing $1,000 worth of needed materials in two $500 lots to avoid soliciting three quotations is not allowed.

Installation of Materials.

Materials purchased must be installed prior to the project expiration date as stated in the Project Agreement.

Reimbursement Guidelines.

This is a reimbursable grant program; therefore, the sponsor must pay the cost(s) up front and then submit a Request for Reimbursement & Project Status Report as provided in this Guide. The sponsor shall specify all costs and value of donations on the Request eligible for reimbursement. Multiple reimbursements may be made throughout the term of the grant in increments not less than 20% of the total grant amount at a time. The final 20% of the grant amount may be withheld until the project is completed and all required documentation has been submitted.

The reimbursement amount will be calculated as a percentage of the incurred costs. For example, for a project where the total project cost is $10,000 with an 80% grant (%8,000), the sponsor's share is 20% ($2,000). If the sponsor submits a partial Request for costs totaling $4,000 to date, then the sponsor's 20% shareis deducted and $3,200 shall be paid, leaving a grant balance of $4,800.

Request #1 costs $4,000  
Sponsor's share -800 (20%)
Grant payment $3,200 (80%)

Assuming all costs as submitted are eligible for reimbursement, payment from the Vermont State Treasurer's Of~ice may be expected in approximately 30 days.

Cash Advance to Trail Grant.

A Requestfor Cash Advance of Trail Grant form may be found in the Application Packet for this program. The FP&R will review each Request on a case-by-case basis and has sole discretion regarding approval.

Guidelines :

Eligible costs for cash advance may include:

Cost Sharing Provisions.

If donated services are applied as part of the sponsor's match, please use the Donated Labor Report found in later in this Guide. Remember to include the donation as a line item on the Request for Reimbursement form. The value of the donation is considered as a real cost for the project and payment is calculated accordingly.

Record Retention.

All program and financial reports shall be retained by the project sponsor until audited by the State of Vermont or for a period of five years after the final close-out date, whichever occurs first. At a minimum, the following records shall be maintained and made available for audit:

Request for Reimbursement & Performance Report.

Refer to the Reimbursement Guidelines earlier in this section.

Donated Labor Report,

This report is for the sponsor's use only. The sponsor may use other record keeping methods that provide at least the information shown on the Report form found later in this section. This information must be retained in the sponsor's files for audit purposes.

Time & Attendance Report for Force Account (Sponsor) Labor.

This report is for the sponsor's use only. The sponsor may use other record keeping methods that provide at least the information shown on the Report form found later in this section. This information must be retained in the sponsor's files for audit purposes.


Copied from the printed publication using a scanner & OCR software on November 15, 1998 by Kenyon F. Karl <railtrails@crosswinds.net> for organizational planning and public informational purposes only. Since unintentional errors are likely, this copy must not be used for grant application or grant compliance purposes!